NWG Murton WTW Upgrade

News & Features

NWG Murton WTW Upgrade

Client: MM Bentley
Date: Aug ‘19 – Jun ’20
Discipline: Electrical Installation

Works included:

  • Installation of cable containment around the perimeter of the treatment hall building
  • High bay lighting.
  • Process plant and equipment installation of cabling and terminations.
  • Waste Water & Contact Tanks,
  • De-Chlorination System
  • External lighting.

In November 2017 Intelect UK Ltd were chosen by MM Bentley as a key electrical installation supplier for a proposed upgrade of an existing borehole water treatment plant at Murton Berwick Upon Tweed. A new water treatment works consisting of pressure filters and chemical dosing was to be constructed off line alongside the existing works and required to be operational by late 2020. Given the relatively short timeframe Intelect were invited to a ‘Design Sprint’ at the Seaham hub where other key suppliers worked collaboratively to formulate an outline design to which prices could be calculated formulating a target overall costs for the scheme. Over the following 14 months MMB designers in Cambridge produced an electrical installation scope and drawing package, this package was received by Intelect for final pricing and an NEC3 Option C design & construct contact was awarded a short time later.

Prior to commencement of site works detailed electrical termination and loop drawings were prepared by Jamie Colledge, these drawings were reviewed and signed off by the clients appointed electrical engineer Dave Bell. Dane Steel was handed the responsibility of supervising the site works and a small team of electricians were assigned to the project with Andy Rudd being in overall charge.

Site installation began in August 2019 with the first activity being the installation of cable containment around the perimeter of the treatment hall building and high bay lighting. Process plant and equipment soon followed opening the way for the installation of cabling and terminations. Before and after pictures of the first stage of works.

Work progressed through the remainder of the year within the treatment hall building and come the Christmas shutdown we were ready to move across to the adjacent High Lift Pumping Station. Between January and March the electrical work within the pumping station was completed enabling the MMB commissioning team to start their testing. It was towards the end of this period that the COVID-19 Pandemic arrived in the UK which had a dramatic effect on the day-to-day progress on not just this project but all other works within Intelect. After a temporary suspension of site works Dane and his team returned to site to see out the remainder of the internal installation works.

At the start of spring our attention turned to field equipment located external to the treatment hall and pumping station, these works included the Waste Water & Contact Tanks, De-Chlorination System and external lighting. Local containment and isolators were mounted then cables we installed through underground ducts, terminations were completed by late May leaving only the external lighting left to essentially complete our works. During the early part of this period we were still working under lockdown conditions but as restrictions started to ease the site team were again able to book into local overnight accommodation allowing for more efficient working and less miles on the road. External lighting and final snagging was completed in late June, the site then went through an evaluation period which at time of writing is still ongoing.

We have received positive feedback for the quality of the electrical installation from both MMB and the end user NWG which is a credit to Dane Steel and his site team, they have all delivered a first class performance under sometimes unprecedented difficult conditions. A total number of 4750hrs were worked on site with no reported incidents or accidents, a great achievement. Another member of the Intelect team ‘the unsung hero’ is Jordan Whelpton - Jordan has had the unenviable task of keeping a commercial eye on the project, providing MMB quantity surveyors with monthly payment applications and the difficult task of answering many queried during the final audit sign off.

My personal thanks to Dane Steel, Andy Rudd, Jamie Colledge and Jordan Whelpton plus all others that have worked on this project.

Kevin Willis

Contracts Manager

More news

3d scanning and point cloud

3D Scanning & Modelling

3D Scanning & Modelling

Our design team use point cloud to produce high resolution, 3D digital models of your plant, buildings and grounds. An invaluable tool for asset and facility management as well as research and develoment projects.

3D Scanning & Modelling

The ultra-portable Focus S70 enables fast, accurate measurements of objects and buildings. It records architectural façades, complex structures, production and supply facilities, accident sites, and large-volume components delivering realistic and true-to-detail scan results.

  • Distance accuracy up to ±1mm.
  • Range from 0.6m up to 70m.
  • IP Class 54.
  • On-Site Compensation.
  • Night Mode scans in low light conditions.
  • On-Site Registration with FARO SCENE.
  • HD photo overlay up to 165 megapixel colour.

Surveying

The ultra-portable Focus S70 enables fast, accurate measurements of objects and buildings. It records architectural façades, complex structures, production and supply facilities, accident sites, and large-volume components delivering realistic and true-to-detail scan results, with a distance accuracy to +/- 1mm. This revolutionary service can be utilised as a single service, or inclusive of Total Turn Key Solution. Not only does it minimise downtime and site disruption, but it also reduces Health and Safety Risks and allows for clash detection.

Production

Through the use of our latest surveying equipment, we are able to produce both 2D and 3D drawings of our client’s sites. With this, we can then produce walkthrough videos for presentations, in addition to in-situ preview designs, which allow you to see the design as it would appear on site once built. This not only improves quality control, but also allows mistakes to be spotted before the build process, saving valuable time and resources.

Services

We are now able to offer point cloud modelling to all new and existing customers.

  • Manipulation of point cloud.
  • Production of 2d drawings.
  • Production of 3d meshes.
  • Walkthrough videos for presentations.
  • Preview designs in-situ.
  • As built drawings.

Benefits

Point cloud modelling is a fast and accurate way to survey your premises.

  • Minimise site disruption / downtime.
  • Reduce Health and Safety risks.
  • Auto desk REVIT compatible.
  • BIM Standard.
  • Faster design process.
  • Clash detection.
  • Quality control.

Case Studies

  • Feasibility Study

    Feasibility Study

    Intelect were contracted by PPG to provide two 3D as-built models of Unit 1 and Unit 2. The model was developed using point-cloud data captured via our Faro Focus 3D S70 Laser ScannerRead More »

Products & Services

  • Decommissioning & Relocation

    Decommissioning & Relocation

    Our plant relocation engineers are experts in their field, and will work with our clients around the clock to ensure the successful move of equipment, whether that be an individual machine, or a full factory relocation.Read More »
  • Mechanical Design & Installation

    Mechanical Design & Installation

    Our mechanical installation capabilities range from installing pipework, to relocating a process plant. At Intelect we have a wide range of skills and expertise across our workforce, enabling us to cater for any size project, across numerous industries.Read More »
  • Electrical Design & Installation

    Electrical Design & Installation

    Our design and engineering services are based on solid foundations developed over many years of working and collaborating with a range of clients across numerous industries.Read More »
Vessels, Pipework & Ducting manufacture and install

Vessels, Pipework & Ducting

Vessels, Pipework & Ducting

Vessels, Pipework & Ducting manufacture and install

Our pipework engineers are skilled in all forms of pipework, across all types of application and industries. We specialise in stainless steel and carbon steel fabrications for food process, utilities and civil engineering industries.

With over 40,000 sq ft of workshop for pipework preparation, we can offer design, procurement and installation, complete with full CDM Management solutions. Our trained fitters and welders are experts in TIG, MMA and MiG, and are fully equipped with the latest flexible LEV systems, in line with the new legislation changes.

We are experts in fully welded stainless steel jacketed pipework, and specialise in process pipework systems for food plants and industrial projects, including steam systems, refrigeration, and compressed air systems.

We have the ability to develop process designs to suit the needs of our customers, including CIP systems and services to a client’s plan and machinery requirements.

Process vessels can be manufactured and provided, or sourced, dependant on client’s budget and needs. We are also able to select suitable pumps and valves that fall in line with established instrumentation.

Systems we provide include:

  • Stainless Steel Pipework Systems
  • Carbon Steel Pipework Systems
  • Mapress Pipework Systems
  • Galvanised Pipework Systems
  • Plastic Pipework Systems
  • Copper Pipework Systems
  • Jacketed Pipework (including heat tracing systems)
  • Process Systems
  • Glycol Pipework
  • Steam Systems
  • CIP Systems
  • CO2 Pipework
  • Gas and Compressed Air Systems
  • Chilled Water Pipework

Case Studies

  • Intelect & KP Snacks, Teesside

    Intelect & KP Snacks, Teesside

    Intelect have been working at the plant since 2000, with John’s team permanently on site since 2005. Their role on the site is split between project, maintenance and repair work to both the production line and the building.Read More »

Products & Services

  • Fabrication Services

    Fabrication Services

    We have fully facilitated, open fabrication workshops, allowing us to fabricate projects, from bespoke parts in most ferrous and non-ferrous materials, to fully integrated services, no matter what the client’s requirements.Read More »
  • Project Management

    Project Management

    One of our greatest strengths is our ability to provide customers with the most complete and fully supported project management service, be that for a small project or a total turn-key solution.Read More »
  • In-house Design

    In-house Design

    Our design and engineering services are based on solid foundations developed over many years of working and collaborating with a range of clients across numerous industries.Read More »
Automated packaging line

Control & Automation

Control & Automation

Intelect’s expert Control & Automation team have the ability to offer both a single or a complete turn-key service to clients, based on the requirements of their project. Services range from design through to installation, and the commissioning of control systems and special purpose machinery.

We have the knowledge and experience required to work across a wide range of environments and industries, including:

  • Food and Beverage Manufacturing
  • Metal Production
  • Utilities
  • Offshore

Over the years, we have established a vast array of satisfied customers across a range of sectors, making us your ideal supplier for Control and Automation system applications.

Our dedicated and committed workforce deliver projects on time and within budget to best suit the client’s needs, satisfactions and schedules.

Control Systems

At Intelect, we have over 20 years’ experience in providing bespoke Control Systems, all of which are designed and built in-house by our expert team of engineers to the current British and European standards and regulations. Our team also ensure the delivery and commissioning of every system, allowing us to support our customers wholly at every stage of the process.

We have experience in providing the following systems:

  • Material Handling and Packaging Control Systems
  • Motor Control Centres
  • LV Switchboards
  • Process and Instrumentation Control Systems
  • PLC and Variable Speed Drive Control Systems
  • Safety Control Systems
  • Hazardous Area Control Systems

Case Studies

Products & Services

  • Total Turn Key Solutions

    Total Turn Key Solutions

    At Intelect, we are a one-stop-shop for your engineering solutions. We have been providing the highest standards of engineering expertise to clients for over 20 years, delivering total turn key projects across a range of industries and sectors.Read More »
  • Bespoke Control Panels

    Bespoke Control Panels

    All of our bespoke panels are built and designed in-house by our team of expertly qualified engineers in our specialised Middlesbrough and Leicester workshops.Read More »
  • In-house Design

    In-house Design

    Our design and engineering services are based on solid foundations developed over many years of working and collaborating with a range of clients across numerous industries.Read More »

News & Features

NWL Howdon Bio-Methane

NWL Howdon Bio-Methane

Case Study : NWL Howdon Bio-Methane

Following on from the success of the Bran Sands PTA Biogas Reuse Project in 2012 NWL once again chose to engage Interserve Construction Ltd as Main Contractor on the new Bio-Methane ‘Gas to Grid’ Project at Howdon.

The success of this project would be measured upon the ability to deliver the project on time, one budget and to the highest quality, As with Bran Sands, Interserve chose Intelect UK Ltd as their preferred electrical sub-contractor based upon our ability to deliver on these success factors.

Work commenced on the site in late July 2014, with the first tasks being the earthing of the formwork within the foundations of the Grid Entry Unit, Pre-Treatment Plant, Bio-Methane Upgrade Plant, Transformer Plinth and, as shown in the picture below the LV Switch Room plinth. Additionally as a part of a dedicated TNS Supply an Earth Rod Nest was installed adjacent to the LV Switch Room.

As well as heavy power distribution there was a significant amount of gas monitoring instrumentation installed, with a large proportion installed within Hazardous Areas. Intelect UK Ltd provide our Installation electricians with ‘CompEx’ training giving them the flexibility to work within many sectors of the production industry including, chemical and petro-chemical. The picture to the right shows one of these Hazardous Area installations, this one being a pressure transmitter and electric actuator at the Pre-Treatment Plant

The overall scale of the project can be seen from the picture to the left. In the foreground we can see the Pre-Treatment Plant with the gas export line disappearing uphill to the Grid Entry Unit. In the background we can see the Plant Rooms and Bio-Methane Process area with the Absorption, Desorption and Flash columns clad in scaffold. To the left are the Propane Storage Tanks with a steel protection cage fitted over

The project brought together contractors from across Europe, all with a common goal of delivering a ‘Gas to Grid’ deadline of the 30th November. The Interserve site project team led by Graeme Eagling kept the project on track and with excellent collaboration between all stakeholders the target date was achieved. We look forward to continuing our good relationships with both Northumbrian Water & Interserve Construction Ltd.

Project Information

Project: NWL Howdon Bio-Methane
Client: Interserve Construction Ltd
Sector: Utilities, Renewables
Discipline: Electrical Installation
Value: Various

Additional Information

Find out more about this project or the services we provided please contact a member of our team: